How Much Concrete Do I Need for a Slab?
Quick answer: concrete = length × width × depth (in feet), then divide by 27 for cubic yards. A 10×10 ft slab at 4 inches deep needs about 1.23 cubic yards, or roughly 61 bags of 80 lb mix. Here's the full formula, depth guidance, and a worked example.
- The concrete formula
- Depth by use (4 in vs 6 in)
- Cubic yards to bags
- Worked example: 10×10 slab
- Ready-mix vs bagged mix
- Common mistakes
The concrete formula
Concrete is measured by volume. Work in feet so the numbers divide cleanly into cubic yards:
Length (ft) × Width (ft) × Depth (ft) = cubic feet, then cubic feet ÷ 27 = cubic yards.
Because depth is usually given in inches, convert first: 4 inches = 4 ÷ 12 = 0.333 ft; 6 inches = 0.5 ft. Add 5–10% waste to your final number.
Depth by use
| Project | Recommended depth | Notes |
|---|---|---|
| Patio / walkway | 4 in | Fine for foot traffic and light loads |
| Garden shed pad | 4 in | Check local code for shed size limits |
| Driveway (cars) | 5–6 in | Reinforce with rebar or wire mesh |
| Structural / footings | 8+ in | Needs an engineer for load design |
Cubic yards to bags
One cubic yard equals 27 cubic feet. If you're mixing bags yourself, standard bag sizes make these volumes:
- 80 lb bag → 0.60 cu ft → about 45 bags per cubic yard
- 60 lb bag → 0.45 cu ft → about 60 bags per cubic yard
- 40 lb bag → 0.30 cu ft → about 90 bags per cubic yard
Worked example: a 10×10 ft slab
- Area = 10 × 10 = 100 sq ft
- Depth = 4 in = 0.333 ft
- Volume = 100 × 0.333 = 33.3 cu ft
- Cubic yards = 33.3 ÷ 27 = 1.23 cu yd
- 80 lb bags = 33.3 ÷ 0.60 = ~56 bags, plus 10% waste → ~61 bags
Ready-mix vs bagged mix
For anything much bigger than a few bags' worth, ready-mix (delivered by truck) is cheaper per cubic yard and saves your back. A rule of thumb: up to about 1 cubic yard, bagged mix is practical; beyond that, get a quote for ready-mix. You'll also need forms, a gravel base, and often rebar — budget those before you order.
Quick lookup: common slab sizes
Here's what common projects need at a 4-inch depth (with ~10% waste added):
| Slab | Volume | Cubic yards | 80 lb bags |
|---|---|---|---|
| 4×4 (small pad) | 5.3 cu ft | 0.2 | ~10 |
| 8×10 (shed) | 26.7 cu ft | 1.0 | ~49 |
| 10×10 (patio) | 33.3 cu ft | 1.2 | ~61 |
| 10×12 (patio) | 40 cu ft | 1.5 | ~73 |
| 12×12 (small driveway) | 48 cu ft | 1.8 | ~88 |
| 20×20 (driveway, 5 in) | 166.7 cu ft | 6.2 | ~306 (or ready-mix) |
A 20×20 driveway is well into ready-mix territory — hauling 300 bags is impractical for most people.
Strength, reinforcement & prep
Bagged mixes are labeled by compressive strength (for example 3,000 or 4,000 psi). Use 3,000 psi for patios and walkways and 4,000+ psi for driveways and anything with vehicle loads. Add rebar or wire mesh for any slab that carries cars, and place it mid-depth so it's actually in tension. Always put a compacted 4-inch gravel base under the slab — concrete poured on soft dirt will crack as it settles.
What it costs
Planning budgets for 2026: ready-mix usually runs $100–$150 per cubic yard, plus a delivery fee. Bagged mix costs more per cubic yard — roughly $150–$250 when you buy bags — but avoids the delivery minimum. On top of either, add forms, gravel base, rebar, and often a finisher. These are estimates; get local quotes for your project.
Pour day checklist
- Gravel base compacted and level.
- Forms set and braced, top edge at finished height.
- Rebar/wire in place and raised to mid-depth.
- Water and finishing tools ready; weather dry.
- Mixer/truck scheduled so you don't run out mid-pour.
Common mistakes
- Mixing up inches and feet. A 4-inch depth written as "4 ft" gives a wildly wrong, oversized order. Convert depth to feet first.
- Forgetting waste. Subgrade is never perfectly level — add 5–10%.
- Ordering ready-mix too tight. A truck can't easily add a little more once it's on site. Round up to the next quarter yard.
- No base. Concrete over soft dirt cracks. Compact a 4-in gravel base first.
FAQ
A 10×10 slab at 4 inches deep is about 1.23 cubic yards, or roughly 56–61 bags of 80 lb mix (with waste). Use the concrete calculator for exact numbers.
4 inches for patios, walkways, and light pads; 5–6 inches for car driveways with reinforcement; 8+ inches for structural footings. Check local code for sheds and driveways.
Ready-mix is cheaper per cubic yard but has a delivery minimum, making it best for larger slabs. Bagged mix is practical up to about 1 cubic yard (roughly 45–60 bags).
One cubic yard covers 81 square feet at 4 inches deep, 54 square feet at 6 inches, and 40.5 square feet at 8 inches. Divide your area by these numbers to find the yards you need.